Category PGS News
WhatsApp 圖片2025 07 2916.28.30 64427c6d

PGS Global Forwarding India Pvt Ltd Project division successfully handled another

Import Breakbulk project cargo to Mumbai Port.

Scope of Work:

  • Destination Unhooking & Inter-carting
  • Destination Custom Clearance
  • Destination Transportation

Overview of the Shipment

  • 127 Packages moved on 2 Original BLs
  • Total of 821995kgs – 2029.62cbm
  • A total 40 Vehicles in use to deliver the cargo at the consignee’s manufacturing unit.
  • 5 vehicles were in used for constant movement for inter-carting
  • 2 BOEs were filed to clear the cargo
  • Took 4 days for the vessel to completely off load the cargo at POD and another 3 days for clearance.
  • 40 heavy vehicles completed the last mile within the planned schedule of 5 to 7 days. 