PGS Global Forwarding India Pvt Ltd Project division successfully handled another
Import Breakbulk project cargo to Mumbai Port.
Scope of Work:
- Destination Unhooking & Inter-carting
- Destination Custom Clearance
- Destination Transportation
Overview of the Shipment
- 127 Packages moved on 2 Original BLs
- Total of 821995kgs – 2029.62cbm
- A total 40 Vehicles in use to deliver the cargo at the consignee’s manufacturing unit.
- 5 vehicles were in used for constant movement for inter-carting
- 2 BOEs were filed to clear the cargo
- Took 4 days for the vessel to completely off load the cargo at POD and another 3 days for clearance.
- 40 heavy vehicles completed the last mile within the planned schedule of 5 to 7 days.